Volunteer Business Analyst · Radio Ramadan UK

Advertising and sponsorship workflow

A community radio station sells advertising to local businesses for its Ramadan broadcasts. Every advert passes through sales, scripting, production, client approval and scheduling, and the hand-offs were hard to see.

Project summary

My role: discovery through to test design and handover

I gathered requirements from management, sponsors and the production team, mapped the current and proposed process, and wrote a business case for standardising the station's existing Trello board. I then defined the user stories and test scenarios, and built a working Trello prototype of the new workflow.

7Process stages mapped
19User stories across 3 epics
14Test scenarios traced to stories
6Handover actions
Organisation
Radio Ramadan, Glasgow
When
June to December 2025
Status
Recommendation made; pilot pending
Tools
Draw.io, Trello, Excel, Word
01InitiationDiscovery, business caseDone 02PlanningAs-is advertising processDone 03DesignTo-be process, use cases, Trello prototypeDone 04Delivery19 user storiesDone 05UAT14 scenarios designed, not yet runDesigned, not run 06BenefitsBaseline measures proposedPending pilot

01 InitiationDiscovery

Seven stages, five roles, many hand-offs

Enquiries arrived by phone, email or outbound sales, then passed through seven stages to broadcast.

The journey of an advert

  1. 1Enquiry
  2. 2Brief
  3. 3Script
  4. 4Record
  5. 5Client review
  6. 6Broadcast order
  7. 7On air

What the team couldn’t easily see

Who said yesWhich enquiries had agreed to go ahead.
Script statusWaiting, in review or approved.
Client sign-offApproved, or changes requested.
DeadlinesDates that later stages depended on.
Broadcast detailsDates and frequency for each advert.

Sources: discovery notes, the 2026 sales report and tariff, and the team’s Trello board. A sample card with an unticked approval checklist was early evidence that sign-off wasn’t being recorded.

01 InitiationBusiness case

Fix the tool they already use

Three options compared on fit, benefit, effort and cost, with benefits to be measured in a pilot rather than claimed.

1 · Keep the current approach

No setup effort, but ownership, deadlines and approval checks stay unclear.

Recommended

2 · Standardise the existing Trello workflow

Agree card fields, a named owner, next action and due date, and stage checklists for requirements and approvals. Builds on a tool the team already knows.

3 · Introduce a separate system

Could add reporting and automation, but needs selection, migration, training and subscriptions. The evidence did not justify it for one campaign.

02 PlanningCurrent state

How it worked before

As-is BPMN swimlane of the Radio Ramadan sponsorship and advertising process
As-is sponsorship and advertising process (BPMN)Four lanes: sponsor, sales and advertising, script and production, and broadcast scheduling. The Trello board tracked broad stages, but nothing checked that the brief was complete or that approvals were recorded before work moved on.

03 DesignFuture state

The proposed process, with controls built in

Proposed to-be BPMN swimlane for sponsorship and advertising
Proposed to-be process (BPMN)One Trello card per booking, with a brief-complete gate before production, internal script approval, recorded client approval, and a check of the broadcast order before scheduling. Click to enlarge; this diagram is wide.

03 DesignUse cases

Who does what in the new workflow

To-be UML use case diagram for Radio Ramadan advertising and sponsorship
To-be use case diagram (UML)Nineteen use cases in three groups (enquiry and booking, advert production and approval, and broadcast scheduling and oversight) across five actors. Each use case became a user story.

03 DesignPrototype

A Trello board the team can adopt

The proposed workflow as a working Trello board: one card per booking, moving across seven lists.

1 · New enquiry
Channel: phone, email or outbound
Owner and next action
2 · Brief and pricing
Contact details and address
30 sec, message, tariff
Repeat-business approval
3 · Script and production
PM approves brief and script
Audio saved to OneDrive and backup
4 · Internal approval
Production Manager approval
Sales Manager approval
5 · Client review
OneDrive review link
Follow-up call, outcome recorded
6 · Ready to schedule
Order signed by both managers
Day or night, dates, frequency
7 · Scheduled
Placed in five-minute break
Conflicts resolved, sequence logged

Rule on every card: the Production Manager updates it after each interaction, revision and progress change, with the outcome, current status and next action. Open the prototype board in Trello →

Wireframe of the proposed RR Adverts 2026 Trello board
Board wireframeDesigned in Draw.io before building the board, so the team could agree the lists and card contents first.

04 DeliveryUser stories

19 user stories with acceptance criteria

Every story traces to the use cases and discovery notes, with confirmed business rules written into the criteria.

IDUser storyAcceptance criteriaPriority
1.1As a sponsor, I want to submit an advertising or sponsorship enquiry, so that Radio Ramadan can follow it up.
  • Staff can access a record of each enquiry
  • It shows advertising, sponsorship or both
Must
1.2As a sponsor, I want to provide campaign details and a brief, so that the station understands my request.
  • Captures business and contact details, message and requested length
  • Missing details are visible before it progresses
Must
1.3As sales staff, I want to record an enquiry and assign an owner, so that someone is responsible for it.
  • An owner can be assigned to each new enquiry
  • The owner is visible on the record
Must
1.4As a sponsor, I want to agree a package and price from the 2026 tariff, so that the booking matches the offer.
  • Agreed price recorded against the tariff
  • Repeat-business discounts need a reason and Sales Manager approval
Must
1.5As sales staff, I want to capture booking requirements and dates, so that production and broadcast can be coordinated.
  • Deliverables and delivery dates recorded
  • Booking stays linked to its enquiry
Must
1.6As sales staff, I want to check the brief is complete, so that gaps are fixed before production.
  • Brief checked against required fields
  • Production Manager approves the brief before scripting
Must
1.7As sales staff, I want to track each booking's owner, status and next action date, so that I can see what needs attention.
  • Owner, status and next action date shown
  • Overdue next actions can be identified
Must
2.1As a sponsor, I want to give the general message and length of my advert, so that a suitable script can be written.
  • Message and length captured on the booking
  • Length checked against available segment time
Must
2.2As production staff, I want to draft a script from the approved brief, so that the advert matches the campaign.
  • Script reflects the message and agreed length
  • Submitted for Production Manager approval before recording
Must
2.3As the Production Manager, I want to review scripts internally, so that issues are fixed before recording.
  • Approval or changes recorded per script version
  • No recording until the script is approved
Must
2.4As production staff, I want to record and edit the advert, so that audio is produced from the approved script.
  • Recording linked to the booking and script
  • Files stored in OneDrive and a backup, with role-based access
Must
2.5As the Production and Sales Managers, we want to check the final advert against the brief, so that problems are caught before the client sees it.
  • Both managers approve before client review
  • Both decisions recorded
Must
2.6As a sponsor, I want to review the advert and approve it or request changes, so that nothing airs without my review.
  • Production Manager shares a OneDrive review link
  • Follow-up call; decision recorded against the version
Must
2.7As the Production Manager, I want to record approval and update the Trello card, so that the team knows it is ready to schedule.
  • Approved version recorded
  • Card updated after every interaction, revision and progress change
Must
3.1As a broadcast scheduler, I want to create a broadcast order from a confirmed booking, so that scheduling uses agreed details.
  • Order shows 30-second length, time of day, dates, frequency and break placement
  • Signed off by both managers
Must
3.2As a broadcast scheduler, I want to schedule adverts into agreed slots, so that delivery follows the order.
  • Adverts run back to back in the five-minute break
  • Day or night timing and sequence recorded; conflicts resolved
Must
3.3As a broadcast scheduler, I want to check the schedule against the order, so that mismatches are fixed before broadcast.
  • Planned sequence compared with the approved order
  • Final schedule recorded with approvals kept
Must
3.4As a manager, I want to review the enquiry and booking pipeline, so that I can see where follow-up is needed.
  • Reviewed at the weekly catch-up
  • Actions recorded with owner and due date
Should
3.5As a manager, I want to monitor outstanding deliverables and deadlines, so that overdue work is chased.
  • Deadlines reviewed weekly
  • Overdue items linked to an owner and action
Should

05 UATTest design

14 test scenarios, traced to the stories

Positive, negative and control tests, including checks that nothing reaches the client or the schedule without the right approvals.

TestStoriesScenarioExpected resultType
TC-011.1, 1.2Record a complete advertising enquiryAll business, contact and brief details saved on one bookingPositive
TC-021.2, 1.6Leave a required field blankMissing field is flagged before the brief goes to productionNegative
TC-031.4Repeat-business price exceptionNot approved until both approvals and the reason are recordedApproval
TC-041.6, 2.2, 2.3Approve brief and script before recordingRecording only starts after script approvalGate
TC-052.4Store files in OneDrive with backupBoth locations recorded; all three staff groups have accessAccess
TC-062.5, 2.6Internal approvals before client reviewBoth manager approvals recorded before the link is sentGate
TC-072.6, 2.7Client approves or requests changesDecision linked to the version; changes keep it in reviewRevision
TC-082.7Update Trello after each interactionCard shows each update, status and next actionRecords
TC-093.1Create and approve a broadcast orderAll fields present; both managers sign before schedulingPositive
TC-103.2Schedule adverts in a five-minute break30-second adverts in order, then normal programming resumesBoundary
TC-113.2, 3.3Two adverts compete for one slotConflict resolved by the named roles and recordedException
TC-123.4, 3.5Weekly pipeline and deadline reviewOverdue work identified; actions get owners and datesReporting
TC-132.5, 2.6Send to client with only one manager approvalBlocked until the second approval is recordedControl
TC-142.6, 3.1, 3.2Schedule before client approvalAdvert stays out of "ready to schedule" until the client approvesControl

06 BenefitsHandover and lessons

What the station needs to decide next

An end-of-project report and handover pack that separate what was agreed from what is still a proposal.

RefOpen actionProposed ownerStatus
HO-01Write the agreed workflow and approvals into one procedureManagement, Sales, ProductionOpen
HO-02Confirm booking fields and how enquiry, advert and approvals linkAdvertising and MarketingOpen
HO-03Confirm break capacity, sequencing and conflict rulesProduction ManagerDecision needed
HO-04Verify the OneDrive folders, backup, access and file namingManagement, ProductionOpen
HO-05Decide whether to adopt the prototype board in the station's workspaceManagement, ProductionDecision needed
HO-06Assign owners, dates and a first review before the next campaignManagementOpen

What went well

  • Process maps, use cases and stories made roles and approval points easy to discuss
  • Building on Trello avoided assuming a new system was needed

What was hard

  • No baseline existed for delays, rework or workload
  • Live adoption depends on the station's own decision and owners

What I'd do next time

  • Agree a business owner and required fields before piloting
  • Set baseline measures, then sample live cards weekly
  • Run the 14 scenarios once the setup is agreed